Study on Performance Factors of Public Building Construction Project in Assosa Zone

Received: 17 March 2022     Accepted: 30 May 2022     Published: 9 June 2022
Views:       Downloads:
Abstract

Construction industry is highly competitive and a job creator for a different groups of expertise such as owners, consultants, contractors and other shareholders. General objectives is to assess the effects of issues determining the presentation of public building construction project in Assosa Zone. The research was used quantitative design; the data was collected from owners, consultants, and contractors using questionnaires and interviews. The performance problems of which the respondents were asked to rank each according to the five-point Likert scale. The results of this research identified 74 factors influencing the performance of public building construction project. From among factors escalation of material prices, unavailability of resources as planned through project duration, sequencing of work according to schedule, differentiation of currency prices, leadership skills of project manager, are the top five significant factors in Assosa zone. To accomplish the public building construction project without delay the clients should hire a specialized engineer and the consultant should give training for the project organization. The contractors should be using the qualified employees with good experience to avoid any problems during construction of the project.

Published in Journal of Civil, Construction and Environmental Engineering (Volume 7, Issue 2)
DOI 10.11648/j.jccee.20220702.12
Page(s) 18-22
Creative Commons

This is an Open Access article, distributed under the terms of the Creative Commons Attribution 4.0 International License (http://creativecommons.org/licenses/by/4.0/), which permits unrestricted use, distribution and reproduction in any medium or format, provided the original work is properly cited.

Copyright

Copyright © The Author(s), 2022. Published by Science Publishing Group

Keywords

Performance Factors, Public Building Construction Project, Top Five Significant Factors

References
[1] A, Al-Shaaby and A, Ahmed (2018). How Do We Measure Project Success? A Survey, Journal of Information Technology & Software Engineering. 08 (02): 1-5.
[2] Ahadzie, D. K., Proverbs, D. G. and Olomolaiye, P. O. (2008). Critical success criteria for mass house building projects in developing countries, International Journal of Project Management. 26 (6): 675–687.
[3] Alsulamy, S., Gupta, N. and Sloan, B. (2014). Factors influencing municipal construction project performance, Proceedings of the Institution of Civil Engineers Municipal Engineer. 167 (2): 108–117.
[4] Chigara, B. and Moyo, T. (2014). Factors Affecting Labor Productivity on Building Projects in Zimbabwe, International Journal of Architecture, Engineering and Construction. 3 (1): 57–65.
[5] Dalcher, D. (2018). Book Review: Global Project Management Handbook: Planning, Organizing, and Controlling International Projects. Second Edition. Project Management.
[6] Enshassi, A., Mohamed, S. and Abushaban, S. (2009). Factors Affecting the Performance of Construction Projects in the Gaza Strip, Journal of Civil Engineering and Management. 15 (3): 269–280.
[7] Fathi, E. and Stevovic, S. (2017). Measurement the efficiency of building project management, Ekonomika. 62 (4): 129–140.
[8] George, D. and Mallery, P. (2003). SPSS for window Step by Step. fourth edition.
[9] Lamprou, A. and Vagiona, D. (2018). Success criteria and critical success factors in project success : a literature review, International Journal of Real Estate and Land Planning. 1 (1): 276–284.
[10] Mirza, M. N., Pourzolfaghar, Z. and Shahnazari, M. (2014). Significance of Scope in Project Success, Procedia Technology. 9 (1): 722–729.
[11] Musa, M. M., Amirudin, R. B., Sofield, T. and Musa, M. A. (2016). Influence of External Environmental Factors on the Success of Public Housing Projects in Developing Countries, Construction Economics and Building. 15 (4): 30–44.
[12] Saraf, D. D. (2013). Study of Factors Affecting Performance of Construction Project, International Journal of Science and Research. 14 (5): 2319–7064.
[13] Siddharth, J., Vyas, C. M. and Pitroda, J. (2015). A critical literature review on comparitive analysis of construction equipments rent and buy, Journal of international academic research for multidisciplinary. 2 (12): 130-141.
[14] Olusola, S. O., Emmanuel, A. O., Omoregie, D. A. and Sakiru, S. A. (2016). Effect of Construction Project Performance on Economic Development of Nigeria. Journal of Economics and Sustainable Development. 7 (12): 142-149.
[15] Onjure, C. O. and Wanyoike, D. M. (2016). Influence of Monitoring and Evaluation Practices on Performance of National Government Funded Construction Projects in Uasin Gishu County-Kenya. International journal of innovative research and development. 5 (12): 78–95.
Cite This Article
  • APA Style

    Aberham Jibat. (2022). Study on Performance Factors of Public Building Construction Project in Assosa Zone. Journal of Civil, Construction and Environmental Engineering, 7(2), 18-22. https://doi.org/10.11648/j.jccee.20220702.12

    Copy | Download

    ACS Style

    Aberham Jibat. Study on Performance Factors of Public Building Construction Project in Assosa Zone. J. Civ. Constr. Environ. Eng. 2022, 7(2), 18-22. doi: 10.11648/j.jccee.20220702.12

    Copy | Download

    AMA Style

    Aberham Jibat. Study on Performance Factors of Public Building Construction Project in Assosa Zone. J Civ Constr Environ Eng. 2022;7(2):18-22. doi: 10.11648/j.jccee.20220702.12

    Copy | Download

  • @article{10.11648/j.jccee.20220702.12,
      author = {Aberham Jibat},
      title = {Study on Performance Factors of Public Building Construction Project in Assosa Zone},
      journal = {Journal of Civil, Construction and Environmental Engineering},
      volume = {7},
      number = {2},
      pages = {18-22},
      doi = {10.11648/j.jccee.20220702.12},
      url = {https://doi.org/10.11648/j.jccee.20220702.12},
      eprint = {https://article.sciencepublishinggroup.com/pdf/10.11648.j.jccee.20220702.12},
      abstract = {Construction industry is highly competitive and a job creator for a different groups of expertise such as owners, consultants, contractors and other shareholders. General objectives is to assess the effects of issues determining the presentation of public building construction project in Assosa Zone. The research was used quantitative design; the data was collected from owners, consultants, and contractors using questionnaires and interviews. The performance problems of which the respondents were asked to rank each according to the five-point Likert scale. The results of this research identified 74 factors influencing the performance of public building construction project. From among factors escalation of material prices, unavailability of resources as planned through project duration, sequencing of work according to schedule, differentiation of currency prices, leadership skills of project manager, are the top five significant factors in Assosa zone. To accomplish the public building construction project without delay the clients should hire a specialized engineer and the consultant should give training for the project organization. The contractors should be using the qualified employees with good experience to avoid any problems during construction of the project.},
     year = {2022}
    }
    

    Copy | Download

  • TY  - JOUR
    T1  - Study on Performance Factors of Public Building Construction Project in Assosa Zone
    AU  - Aberham Jibat
    Y1  - 2022/06/09
    PY  - 2022
    N1  - https://doi.org/10.11648/j.jccee.20220702.12
    DO  - 10.11648/j.jccee.20220702.12
    T2  - Journal of Civil, Construction and Environmental Engineering
    JF  - Journal of Civil, Construction and Environmental Engineering
    JO  - Journal of Civil, Construction and Environmental Engineering
    SP  - 18
    EP  - 22
    PB  - Science Publishing Group
    SN  - 2637-3890
    UR  - https://doi.org/10.11648/j.jccee.20220702.12
    AB  - Construction industry is highly competitive and a job creator for a different groups of expertise such as owners, consultants, contractors and other shareholders. General objectives is to assess the effects of issues determining the presentation of public building construction project in Assosa Zone. The research was used quantitative design; the data was collected from owners, consultants, and contractors using questionnaires and interviews. The performance problems of which the respondents were asked to rank each according to the five-point Likert scale. The results of this research identified 74 factors influencing the performance of public building construction project. From among factors escalation of material prices, unavailability of resources as planned through project duration, sequencing of work according to schedule, differentiation of currency prices, leadership skills of project manager, are the top five significant factors in Assosa zone. To accomplish the public building construction project without delay the clients should hire a specialized engineer and the consultant should give training for the project organization. The contractors should be using the qualified employees with good experience to avoid any problems during construction of the project.
    VL  - 7
    IS  - 2
    ER  - 

    Copy | Download

Author Information
  • Department of Construction Technology & Management, College of Engineering, Assosa University, Assosa, Ethiopia

  • Sections