Abstract

All most all projects that are development oriented in different areas and different countries, even if they are completed, they will not be successfully implemented on the scheduled time or may not be on the budgeted time frame or they will not be on the expected quality due to different factors. The major objective of this study is to determine factors that affect the successful implementation of development projects in Amhara national regional state. To come up with this objective the raw data was collected from Amhara building construction enterprise, Menkorer constriction enterprise and Amhara national regional state administration office. The researcher used a mixed research approach which is both quantitative and qualitative research approaches. The sampling technique used was Stratified judgmental non probability method to select proportional number of samples from the target population of the study. The raw data was analyzed by using multiple linear regression analysis method. The findings of the research output were identified as problems which are related with the release of project funds on time, shortage of raw materials during construction and poor project planning and preparation negatively affects the successful implementation of development projects within the region. After identifying the problems based on the output of the study, the researcher suggests the most possible ways to alleviate the problems.

Published in American Journal of Theoretical and Applied Business (Volume 7, Issue 4)
DOI 10.11648/j.ajtab.20210704.13
Page(s) 90-97
Creative Commons

This is an Open Access article, distributed under the terms of the Creative Commons Attribution 4.0 International License (http://creativecommons.org/licenses/by/4.0/), which permits unrestricted use, distribution and reproduction in any medium or format, provided the original work is properly cited.

Copyright

Copyright © The Author(s), 2021. Published by Science Publishing Group

Keywords

Project, Success, Project Funds, Implementation, Amhara Region

References
[1] Erik Versuh (2003), The Portable MBA in Project Management, USA.
[2] Antill, J. M. (1974), Project management: an overall concept, I. E. Aust, Adelaide, Keynote Address to Project Management Symposium, South Australian Division.
[3] PMI, (2015) A guides to the project management body of knowledge (PMBOK Guide) fourth edition.
[4] Flaman & Gallagher, (2001). Measuring Project Success, Project Management Journal 23 (1): 8-17.
[5] Robers Frese & Dr. Vicky Sauter (2003) Project success and failure: What is success, What is failure, and how can you improve your ODDS for performance?
[6] Geneva (2011), Domestic workers convention: international
[7] PMI, (2008) A guides to the project management body of knowledge (PMBOK Guide) fourth edition.
[8] Mark freeman & Peter Beale (2015) Measuring project success: Project management journal.
[9] PMI, (2014) A guides to the project management body of knowledge (PMBOK Guide) fourth edition labor organization: No 189.
[10] Kirubel Hailu, (2008), Factors Affecting the Success of Project Implementation: The Caseof World Vision Ethiopia, master’s thesis paper for graduation.
[11] Blen damtew (2019), Factors Affecting Successful Implementation of Projects in International Nongovernmental Organizations in Ethiopia: The case of Save the Children International Projects Master’s Thesis.
[12] Mekdes Getaye, (2017), Assessment of Factors Affecting Project Implementation: The Case of Aacra Ferensay Biret Dildiy-Satelayt Tabiya Road Construction Master’s Thesis.
[13] Ameh E. et al, (2011) Paediaric surgery: a comprehensive text for Africa.
[14] Tawil (2013) two roads ahead for education – which one should we take: DVV international journal, vol 80, issue 1, pages 115–119.
[15] Behailu ayele woldesemaite (2018) Factors affecting the successful implementation of rural electrification projects in Ethiopia: National academic digital repository of Ethiopia.
Cite This Article
  • APA Style

    Zewdu Eskezia Gelaye, Birhanu Daba Chali, Solomon Asfaw, Kidane Alemu Ago, Bazezew Endalew Abegaz. (2021). Factors that Affect Successful Implementation of Development Projects in Amhara Region: A Case of Amhara Building and Menkorer Construction Enterprises. American Journal of Theoretical and Applied Business, 7(4), 90-97. https://doi.org/10.11648/j.ajtab.20210704.13

    Copy | Download

    ACS Style

    Zewdu Eskezia Gelaye; Birhanu Daba Chali; Solomon Asfaw; Kidane Alemu Ago; Bazezew Endalew Abegaz. Factors that Affect Successful Implementation of Development Projects in Amhara Region: A Case of Amhara Building and Menkorer Construction Enterprises. Am. J. Theor. Appl. Bus. 2021, 7(4), 90-97. doi: 10.11648/j.ajtab.20210704.13

    Copy | Download

    AMA Style

    Zewdu Eskezia Gelaye, Birhanu Daba Chali, Solomon Asfaw, Kidane Alemu Ago, Bazezew Endalew Abegaz. Factors that Affect Successful Implementation of Development Projects in Amhara Region: A Case of Amhara Building and Menkorer Construction Enterprises. Am J Theor Appl Bus. 2021;7(4):90-97. doi: 10.11648/j.ajtab.20210704.13

    Copy | Download

  • @article{10.11648/j.ajtab.20210704.13,
      author = {Zewdu Eskezia Gelaye and Birhanu Daba Chali and Solomon Asfaw and Kidane Alemu Ago and Bazezew Endalew Abegaz},
      title = {Factors that Affect Successful Implementation of Development Projects in Amhara Region: A Case of Amhara Building and Menkorer Construction Enterprises},
      journal = {American Journal of Theoretical and Applied Business},
      volume = {7},
      number = {4},
      pages = {90-97},
      doi = {10.11648/j.ajtab.20210704.13},
      url = {https://doi.org/10.11648/j.ajtab.20210704.13},
      eprint = {https://article.sciencepublishinggroup.com/pdf/10.11648.j.ajtab.20210704.13},
      abstract = {All most all projects that are development oriented in different areas and different countries, even if they are completed, they will not be successfully implemented on the scheduled time or may not be on the budgeted time frame or they will not be on the expected quality due to different factors. The major objective of this study is to determine factors that affect the successful implementation of development projects in Amhara national regional state. To come up with this objective the raw data was collected from Amhara building construction enterprise, Menkorer constriction enterprise and Amhara national regional state administration office. The researcher used a mixed research approach which is both quantitative and qualitative research approaches. The sampling technique used was Stratified judgmental non probability method to select proportional number of samples from the target population of the study. The raw data was analyzed by using multiple linear regression analysis method. The findings of the research output were identified as problems which are related with the release of project funds on time, shortage of raw materials during construction and poor project planning and preparation negatively affects the successful implementation of development projects within the region. After identifying the problems based on the output of the study, the researcher suggests the most possible ways to alleviate the problems.},
     year = {2021}
    }
    

    Copy | Download

  • TY  - JOUR
    T1  - Factors that Affect Successful Implementation of Development Projects in Amhara Region: A Case of Amhara Building and Menkorer Construction Enterprises
    AU  - Zewdu Eskezia Gelaye
    AU  - Birhanu Daba Chali
    AU  - Solomon Asfaw
    AU  - Kidane Alemu Ago
    AU  - Bazezew Endalew Abegaz
    Y1  - 2021/11/05
    PY  - 2021
    N1  - https://doi.org/10.11648/j.ajtab.20210704.13
    DO  - 10.11648/j.ajtab.20210704.13
    T2  - American Journal of Theoretical and Applied Business
    JF  - American Journal of Theoretical and Applied Business
    JO  - American Journal of Theoretical and Applied Business
    SP  - 90
    EP  - 97
    PB  - Science Publishing Group
    SN  - 2469-7842
    UR  - https://doi.org/10.11648/j.ajtab.20210704.13
    AB  - All most all projects that are development oriented in different areas and different countries, even if they are completed, they will not be successfully implemented on the scheduled time or may not be on the budgeted time frame or they will not be on the expected quality due to different factors. The major objective of this study is to determine factors that affect the successful implementation of development projects in Amhara national regional state. To come up with this objective the raw data was collected from Amhara building construction enterprise, Menkorer constriction enterprise and Amhara national regional state administration office. The researcher used a mixed research approach which is both quantitative and qualitative research approaches. The sampling technique used was Stratified judgmental non probability method to select proportional number of samples from the target population of the study. The raw data was analyzed by using multiple linear regression analysis method. The findings of the research output were identified as problems which are related with the release of project funds on time, shortage of raw materials during construction and poor project planning and preparation negatively affects the successful implementation of development projects within the region. After identifying the problems based on the output of the study, the researcher suggests the most possible ways to alleviate the problems.
    VL  - 7
    IS  - 4
    ER  - 

    Copy | Download

Author Information
  • College of Business and Economics, Department of Accounting and Finance, Dembi Dollo University, Dembi Dollo, Ethiopia

  • College of Business and Economics, Department of Accounting and Finance, Dembi Dollo University, Dembi Dollo, Ethiopia

  • College of Business and Economics, Department of Accounting and Finance, Debre Birhan University, Debre Birhan, Ethiopia

  • College of Business and Economics, Department of Economics, Dembi Dollo University, Dembi Dollo, Ethiopia

  • College of Business and Economics, Department of Economics, Mekdelamba University, Mekdelamba, Ethiopia

  • Sections