Due to the reduce of the national investment and technology development, the market environment changes rapidly and the competition become more and more fierce, the situation require companies to improve the management level, at the same time the uncertainty and the complexity of construction projects also increase sharply, competition for scarce resources gradually intensified, all those factors leading to more and more difficult to complete the project timely, this paper adopt Delphi method to identify schedule risk, by introducing the severity index and important index as secondary indexes, through schedule risk analysis to determine the schedule risk control valve value (sensitivity index), take the sensitivity index as a valid trigger out decision basis of action, to build a comprehensive (project - activity layer) framework of project schedule risk identification, monitoring and correction organization. It can help project manager to identify the risk in advance, good for adopt some measures to control the risk and make the goal come true.
Published in | Journal of Civil, Construction and Environmental Engineering (Volume 2, Issue 1) |
DOI | 10.11648/j.jccee.20170201.11 |
Page(s) | 1-6 |
Creative Commons |
This is an Open Access article, distributed under the terms of the Creative Commons Attribution 4.0 International License (http://creativecommons.org/licenses/by/4.0/), which permits unrestricted use, distribution and reproduction in any medium or format, provided the original work is properly cited. |
Copyright |
Copyright © The Author(s), 2017. Published by Science Publishing Group |
Sczhedule Risk Analysis, The Sensitivity Index, Control Valve Value
[1] | Ching-wen chang, Li Renan. Critical chain project scheduling method research [J]. Control and decision, 2013, 28 (9): 1281-1286. |
[2] | Xu Xiaofeng, li xiang, jia-guo liu. Critical chain project resource planning schedule variance warning control model [J]. Journal of systems engineering, 2014, 29 (6): 845-851. |
[3] | Wang Weixin. Under uncertain environment of multi-project scheduling research [D]. Chongqing university, 2014. |
[4] | Hulett D T. Schedule risk analysis simplified [M]. Project Management Network, 1996. |
[5] | Davidson, Jeff. 2000. 10 Minute Guide to Project Management. Indianapolis: Macmillan. (ISBN 0-02-863966-9). |
[6] | Conway, Kieron. 2001. Software Project Management: From Concept to Deployment. Scottsdale, Ariz.: The Coriolis Group. (ISBN 1-57610-807-4). |
[7] | Goodpasture, John C. 2002. Managing Projects for Value. Vienna, Va.: Management Concpets. (ISBN1-56726-138-8). |
[8] | Levine, Harvey A. 2002. Practical Project Management: Tips, Tactics, and Tools. New York: John Wiley & Sons, Inc. (ISBN 0-471-20303-3). |
[9] | Lewis, James. T eam-Based Project Management. Beard Books, 2003. |
[10] | Project Planning, Scheduling, and Control, Fourth edition. New York: McGraw-Hill, 2006. |
[11] | Wysocki, Robert K., and James P. Lewis. The World-Class Project Manager. Boston: Perseus, 2000. |
APA Style
Qingyue Gu, Chunjing Liu. (2017). The Project Schedule Control Method Under the Influence of Uncertain Factors and Resource Constraints. Journal of Civil, Construction and Environmental Engineering, 2(1), 1-6. https://doi.org/10.11648/j.jccee.20170201.11
ACS Style
Qingyue Gu; Chunjing Liu. The Project Schedule Control Method Under the Influence of Uncertain Factors and Resource Constraints. J. Civ. Constr. Environ. Eng. 2017, 2(1), 1-6. doi: 10.11648/j.jccee.20170201.11
@article{10.11648/j.jccee.20170201.11, author = {Qingyue Gu and Chunjing Liu}, title = {The Project Schedule Control Method Under the Influence of Uncertain Factors and Resource Constraints}, journal = {Journal of Civil, Construction and Environmental Engineering}, volume = {2}, number = {1}, pages = {1-6}, doi = {10.11648/j.jccee.20170201.11}, url = {https://doi.org/10.11648/j.jccee.20170201.11}, eprint = {https://article.sciencepublishinggroup.com/pdf/10.11648.j.jccee.20170201.11}, abstract = {Due to the reduce of the national investment and technology development, the market environment changes rapidly and the competition become more and more fierce, the situation require companies to improve the management level, at the same time the uncertainty and the complexity of construction projects also increase sharply, competition for scarce resources gradually intensified, all those factors leading to more and more difficult to complete the project timely, this paper adopt Delphi method to identify schedule risk, by introducing the severity index and important index as secondary indexes, through schedule risk analysis to determine the schedule risk control valve value (sensitivity index), take the sensitivity index as a valid trigger out decision basis of action, to build a comprehensive (project - activity layer) framework of project schedule risk identification, monitoring and correction organization. It can help project manager to identify the risk in advance, good for adopt some measures to control the risk and make the goal come true.}, year = {2017} }
TY - JOUR T1 - The Project Schedule Control Method Under the Influence of Uncertain Factors and Resource Constraints AU - Qingyue Gu AU - Chunjing Liu Y1 - 2017/01/16 PY - 2017 N1 - https://doi.org/10.11648/j.jccee.20170201.11 DO - 10.11648/j.jccee.20170201.11 T2 - Journal of Civil, Construction and Environmental Engineering JF - Journal of Civil, Construction and Environmental Engineering JO - Journal of Civil, Construction and Environmental Engineering SP - 1 EP - 6 PB - Science Publishing Group SN - 2637-3890 UR - https://doi.org/10.11648/j.jccee.20170201.11 AB - Due to the reduce of the national investment and technology development, the market environment changes rapidly and the competition become more and more fierce, the situation require companies to improve the management level, at the same time the uncertainty and the complexity of construction projects also increase sharply, competition for scarce resources gradually intensified, all those factors leading to more and more difficult to complete the project timely, this paper adopt Delphi method to identify schedule risk, by introducing the severity index and important index as secondary indexes, through schedule risk analysis to determine the schedule risk control valve value (sensitivity index), take the sensitivity index as a valid trigger out decision basis of action, to build a comprehensive (project - activity layer) framework of project schedule risk identification, monitoring and correction organization. It can help project manager to identify the risk in advance, good for adopt some measures to control the risk and make the goal come true. VL - 2 IS - 1 ER -