The COVID-19 pandemic affected all urban and rural areas across the globe. Particularly, the pandemic disrupted the material supply impacting all project schedules and project decisions. The purpose of this study is to analyze the materials delay impact due to COVID-19 pandemic on construction projects in terms of their schedule decisions. This study used an online questionnaire survey to collect the data from executive members of the construction companies within the United States. The survey focused on material supply and delivery delay questions organized in two subgroups using the Construction Specifications Institute MasterFormat divisions: (1) Facility Services and (2) Site and Infrastructure. Thirty-two responses from diverse company executive members were analyzed using t-test. The findings indicated that most of the projects were delayed due to either “Material and Labor” or “Material, Labor, and Equipment.” Thus, the two groups were analyzed in depth. The analysis shows that the mean delays were significantly higher for the “Material, Labor, and Equipment” group than the “Material and Labor” group. This is an important finding, suggesting that if similar situations arise, the project managers and/or the decision-makers should consider dedicating their time to the equipment required for those divisions and therefore mitigate delays. The study identifies crucial insights for successful project management during the pandemic, emphasizing the necessity of collaborating with subcontractors to secure essential equipment and address delays. It suggests expediting contract buyouts and submittals in vulnerable divisions to enhance resilience against material supply disruptions. Timely material procurement following project approvals for various durations is vital for minimizing pandemic-induced delays. Additionally, the study recommends adjusting lead times for materials with extended delivery timelines to mitigate construction delays associated with the pandemic. The lesson learned and recommendations from this study contributes to the body of knowledge in project management and project decision making by helping project managers and engineers to understand the impact and awareness of the challenges in material supply disruption during COVID-19 pandemic that could assist managers formulate appropriate strategies on future potential outbreaks.
Published in | Science, Technology & Public Policy (Volume 7, Issue 2) |
DOI | 10.11648/j.stpp.20230702.14 |
Page(s) | 75-84 |
Creative Commons |
This is an Open Access article, distributed under the terms of the Creative Commons Attribution 4.0 International License (http://creativecommons.org/licenses/by/4.0/), which permits unrestricted use, distribution and reproduction in any medium or format, provided the original work is properly cited. |
Copyright |
Copyright © The Author(s), 2023. Published by Science Publishing Group |
Material Supply Disruption, Construction Delays, COVID-19 Impact, Project Management
[1] | T. Umar. The impact of COVID-19 on the GCC construction industry, International Journal of Service Science, Management, Engineering, and Technology (IJSSMET), 13(2), 1-17, 2022. |
[2] | S. K. Ganji. Leveraging the World Cup: Mega sporting events, human rights risk, and worker welfare reform in Qatar, Journal on Migration and Human Security, 4(4), 221-259, 2016. |
[3] | T. Umar, C. Egbu, M. S. Honnurvali, M. Saidani, and Al-A. J. Bayati. Briefing: Status of occupational safety and health in GCC construction. Proceedings of the institution of civil engineers-management, procurement and law, 172(4), 137-141, 2019. |
[4] | CDC (Centers for Disease Control and Prevention). Online available from https://data.cdc.gov/ Accessed June 15, 2021. |
[5] | R. F. Pasco, S. J. Fox, S. C. Johnston, M. Pignone, and L. A. Meyers. Estimated association of construction work with risks of COVID-19 infection and hospitalization in Texas. JAMA network open, 3(10), e2026373, 2020. doi: 10.1001/jamanetworkopen.2020.26373. |
[6] | S. Brown, R. Brooks, X. S., and Dong. Impact of COVID-19 on Construction Businesses and Productions. CPWR Data Bulletin. Online available from https://www.cpwr.com/wp-content/uploads/DataBulletin-November2020.pdf |
[7] | Y. Gamil and A. Alhagar. The Impact of Pandemic Crisis on the Survival of Construction Industry: A Case of COVID-19, Mediterranean Journal of Social Sciences 11(4), 122-128, 2020. |
[8] | H. Shen, M. Fu, H. Pan, Z. Yu, and Y. Chen. The impact of the COVID-19 pandemic on firm performance. Emerging Markets Finance and Trade, 56(10), 2213-2230, 2020. |
[9] | J. Gallagher. Construction Guidance for COVID-19. Online available from https://www.ajg.com/us/news-and-insights/2020/mar/construction-guidance-for-coronavirus-covid-19-pandemic/ |
[10] | R. C. Epstein, Z. D. Knaub, S. C. Russo, D. C. Jensen, J. L. Mascialino. For Developers and Owners: How COVID-19 Is Affecting Construction Projects and Actions You Should Consider. Online available from https://www.natlawreview.com/article/developers-and-owners-how-covid-19-affecting-construction-projects-and-actions-you |
[11] | WHO (World Health Organization). Coronavirus Disease (COVID-19). Online available from https://www.who.int/emergencies/diseases/novel-coronavirus-2019. |
[12] | T. Al Amri M. Marey-Perez. Impact of Covid-19 on Oman’s construction industry. Technium Social Sciences Journal, 9, 661-670, 2020. |
[13] | G. Denny-Smith, R. Y. Sunindijo, M. Loosemore, M. Williams, M., and L. Piggott. How Construction Employment Can Create Social Value and Assist Recovery from COVID-19. Sustainability, 13(2), p. 988, 2020. |
[14] | M. B. Esa, F. S. B. Ibrahim, and E. B. M. Kamal. Covid-19 pandemic lockdown: The consequences towards project success in Malaysian construction industry. Advances in Science, Technology and Engineering Systems Journal, 5(5), 973-983, 2020. |
[15] | V. Kaushal and M. Najafi. Strategies to mitigate COVID-19 pandemic impacts on health and safety of workers in construction projects. Civil Engineering Beyond Limits, 2, 1-8, 2021. |
[16] | L. T. Allan-Blitz, I. Turner, F. Hertlein, and J. D. Klausner. High frequency and prevalence of community-based asymptomatic SARS-CoV-2 infection. medRxiv, doi: 10.1101/2020.12.09.20246249. |
[17] | A. Alsharef, S. Banerjee, S. M. Jamil Uddin, A. Albert, and E. Jaselskis. Early impacts of the COVID-19 pandemic on the United States construction industry. International Journal of Environmental Research and Public Health, 18 (4), p. 1559, 2021. |
[18] | S. D. Choi, and J. A. Staley. Safety and Health Implications of COVID-19 on the United States Construction Industry. Industrial and Systems Engineering Review, 9(1), 56-67, 2021. |
[19] | M. Gunduz, and B. Ahsan. Construction safety factors assessment through Frequency Adjusted Importance Index. International Journal of Industrial Ergonomics, 64, 155-162, 2018. |
[20] | M. Loosemore, and N. Malouf. Safety training and positive safety attitude formation in the Australian construction industry. Safety Science, 113, 233-243, 2019. |
[21] | M. Namian, A. Albert, C. M. Zuluaga, and M. Behm. Role of safety training: Impact on hazard recognition and safety risk perception. Journal of construction engineering and management, 142(12), 04016073, 2016. |
[22] | B. Pandit, A. Albert, Y. Patil, and A. J. Al-Bayati. Impact of safety climate on hazard recognition and safety risk perception. Safety Science, 113, 44-53, 2019. |
[23] | S. M. J. Uddin, A. Albert, A. Alsharef, B. Pandit, Y. Patil, and C. Nnaji. Hazard Recognition Patterns Demonstrated by Construction Workers. International Journal of Environmental Research and Public Health, 17(21), 7788, 2020. |
[24] | O. A. Ayodele, A. Chang-Richards, and V. González, Factors Affecting Workforce Turnover in the Construction Sector: A Systematic Review. Journal of Construction Engineering and Management, 146(2), 03119010, 2020. |
[25] | C. Heigl. 7 Major Trends That Will Impact the Construction Industry. Construction Industry News. Online available from https://www.constructconnect.com/blog/7-major-trends-will-impact-construction-industry. |
[26] | J. Rodriguez. Managing Five Generations at the Construction Site. Communication and Integration Are Essential for Success. Online available from https://www.thebalancesmb.com/managing-different-generations-in-construction-4137829 |
[27] | A. Zidan, A. Mousa, and M. Mahgoub. A survey-based vision for restructuring concrete business in the new residential communities in Egypt. Industrial and Systems Engineering Review, 1(2), 162-172, 2013. |
[28] | Assaf, and S. Al-Hejji. Causes of delay in large construction projects. International journal of project management, 24(4), pp. 349-357, 2006. |
[29] | A. H. Al-Momani. Construction delay: a quantitative analysis. International journal of project management, 18(1), 51-59, 2000. |
[30] | D. W. Chan, and M. M. Kumaraswamy. A comparative study of causes of time overruns in Hong Kong construction projects. International Journal of project management, 15(1), 55-63, 1997. |
[31] | P. F. Kaming, P. O. Olomolaiye, G. D. Holt, and F. C. Harris. Factors influencing construction time and cost overruns on high-rise projects in Indonesia. Construction Management and Economics, 15(1), 83-94, 1997. |
[32] | I. B. Gurbuz, and G. Ozkan, G. Transform or perish: Preparing the business for a postpandemic future. IEEE Engineering Management Review, 48(3), 139-145, 2020. |
[33] | L. M. Koonin. Novel coronavirus disease (COVID-19) outbreak: Now is the time to refresh pandemic plans. Journal of business continuity and emergency planning, 13(4), 298-312, 2020. |
[34] | A. S. Hammadi, and M. S. Nawab. Study of delay factors in construction projects. International Advanced Research Journal in Science, Engineering and Technology, 3(4), 87-93, 2016. |
[35] | J. H. Thun, J. H. and D. Hoenig. An empirical analysis of supply chain risk management in the German automotive industry. International journal of production economics, 131(1), pp. 242-249, 2011. |
[36] | D. Ivanov. Predicting the impacts of epidemic outbreaks on global supply chains: A simulation-based analysis on the coronavirus outbreak (COVID-19/SARS-CoV-2) case. Transportation Research Part E: Logistics and Transportation Review, 136, 101922, 2020. |
[37] | P. Chowdhury, S. K. Paul, S. Kaisar, and M. A. Moktadir. COVID-19 pandemic related supply chain studies: A systematic review. Transportation Research Part E: Logistics and Transportation Review, 148, 102271, 2021. |
[38] | T. Ibn-Mohammed, K. B. Mustapha, J. Godsell, Z. Adamu, K. A. Babatunde, D. D. Akintade, A. Acquaye, H. Fujii, M. M. Ndiaye, F. A. Yamoah, and S. C. L. Koh. A critical analysis of the impacts of COVID-19 on the global economy and ecosystems and opportunities for circular economy strategies. Resources, Conservation and Recycling, 164, 105169, 2021. |
[39] | M. Sharma, S. Luthra, S. Joshi, and A. Kumar. Developing a framework for enhancing survivability of sustainable supply chains during and post-COVID-19 pandemic. International Journal of Logistics Research and Applications, 25(4-5), 433-453, 2022. |
[40] | T. M. Choi. Innovative “bring-service-near-your-home” operations under Corona-virus (COVID-19/SARS-CoV-2) outbreak: Can logistics become the messiah?. Transportation Research Part E: Logistics and Transportation Review, 140, 101961, 2020. |
[41] | M. An, C. Baker, and J. Zeng. A fuzzy-logic-based approach to qualitative risk modelling in the construction process. World journal of engineering, 2, pp. 1-12, 2005. |
[42] | L. G. Selyutina. Innovative approach to managerial decision-making in construction business. In Materials Science Forum Trans Tech Publications Ltd. Vol. 931, pp. 1113-1117, 2018. |
[43] | C. M. Harper, and T. Sulbaran. Measuring the reliability of construction decision making inventory in construction management. In Proc. of the 55th ASC Annual International Conference, April (pp. 10-13), 2019. |
[44] | A. Sharifi, and A. R. Khavarian-Garmsir. The COVID-19 pandemic: Impacts on cities and major lessons for urban planning, design, and management. Science of the Total Environment, 749, 142391, 2020. |
[45] | A. S. Butt. Strategies to mitigate the impact of COVID-19 on supply chain disruptions: a multiple case analysis of buyers and distributors. The international journal of logistics management. doi: 10.1108/IJLM-11-2020-0455. |
[46] | W. McKibbin and R. Fernando. The global macroeconomic impacts of COVID-19: Seven scenarios. Asian Economic Papers, 20(2), pp. 1-30, 2021. |
[47] | P. Cleave. What Is A Good Survey Response Rate? Smart Survey. Online available from https://www.smartsurvey.co.uk/blog/what-is-a-good-survey-response-rate |
[48] | A. E. M. Ali, I. A. HAl-Sulaihi, and K. S. Al-Gahtani. Indicators for measuring performance of building construction companies in Kingdom of Saudi Arabia. Journal of King Saud University-Engineering Sciences, 25(2), 125-134, 2013. |
[49] | F. D. Cherkos, and K. N. Jha. Suitability and Performance Indicators of Toll Road Delivery Methods. Journal of Legal Affairs and Dispute Resolution in Engineering and Construction, 13(2), 05021002, 2021. |
[50] | L. Kish. Survey Sampling. John Wiley and Sons Inc., New York, 1995. |
[51] | K. K. Tripathi, and K. N. Jha. An empirical study on performance measurement factors for construction organizations. KSCE journal of civil engineering, 22(4), 1052-1066, 2018. |
[52] | P. D. Ellis, P. D. The essential guide to effect sizes: Statistical power, meta-analysis, and the interpretation of research results. Cambridge university press, 2020. |
APA Style
Kisi, K., Sulbaran, T. (2023). Mitigating Construction Delays: Lessons from the COVID-19 Pandemic on Material Supply Disruptions. Science, Technology & Public Policy, 7(2), 75-84. https://doi.org/10.11648/j.stpp.20230702.14
ACS Style
Kisi, K.; Sulbaran, T. Mitigating Construction Delays: Lessons from the COVID-19 Pandemic on Material Supply Disruptions. Sci. Technol. Public Policy 2023, 7(2), 75-84. doi: 10.11648/j.stpp.20230702.14
AMA Style
Kisi K, Sulbaran T. Mitigating Construction Delays: Lessons from the COVID-19 Pandemic on Material Supply Disruptions. Sci Technol Public Policy. 2023;7(2):75-84. doi: 10.11648/j.stpp.20230702.14
@article{10.11648/j.stpp.20230702.14, author = {Krishna Kisi and Tulio Sulbaran}, title = {Mitigating Construction Delays: Lessons from the COVID-19 Pandemic on Material Supply Disruptions}, journal = {Science, Technology & Public Policy}, volume = {7}, number = {2}, pages = {75-84}, doi = {10.11648/j.stpp.20230702.14}, url = {https://doi.org/10.11648/j.stpp.20230702.14}, eprint = {https://article.sciencepublishinggroup.com/pdf/10.11648.j.stpp.20230702.14}, abstract = {The COVID-19 pandemic affected all urban and rural areas across the globe. Particularly, the pandemic disrupted the material supply impacting all project schedules and project decisions. The purpose of this study is to analyze the materials delay impact due to COVID-19 pandemic on construction projects in terms of their schedule decisions. This study used an online questionnaire survey to collect the data from executive members of the construction companies within the United States. The survey focused on material supply and delivery delay questions organized in two subgroups using the Construction Specifications Institute MasterFormat divisions: (1) Facility Services and (2) Site and Infrastructure. Thirty-two responses from diverse company executive members were analyzed using t-test. The findings indicated that most of the projects were delayed due to either “Material and Labor” or “Material, Labor, and Equipment.” Thus, the two groups were analyzed in depth. The analysis shows that the mean delays were significantly higher for the “Material, Labor, and Equipment” group than the “Material and Labor” group. This is an important finding, suggesting that if similar situations arise, the project managers and/or the decision-makers should consider dedicating their time to the equipment required for those divisions and therefore mitigate delays. The study identifies crucial insights for successful project management during the pandemic, emphasizing the necessity of collaborating with subcontractors to secure essential equipment and address delays. It suggests expediting contract buyouts and submittals in vulnerable divisions to enhance resilience against material supply disruptions. Timely material procurement following project approvals for various durations is vital for minimizing pandemic-induced delays. Additionally, the study recommends adjusting lead times for materials with extended delivery timelines to mitigate construction delays associated with the pandemic. The lesson learned and recommendations from this study contributes to the body of knowledge in project management and project decision making by helping project managers and engineers to understand the impact and awareness of the challenges in material supply disruption during COVID-19 pandemic that could assist managers formulate appropriate strategies on future potential outbreaks. }, year = {2023} }
TY - JOUR T1 - Mitigating Construction Delays: Lessons from the COVID-19 Pandemic on Material Supply Disruptions AU - Krishna Kisi AU - Tulio Sulbaran Y1 - 2023/11/30 PY - 2023 N1 - https://doi.org/10.11648/j.stpp.20230702.14 DO - 10.11648/j.stpp.20230702.14 T2 - Science, Technology & Public Policy JF - Science, Technology & Public Policy JO - Science, Technology & Public Policy SP - 75 EP - 84 PB - Science Publishing Group SN - 2640-4621 UR - https://doi.org/10.11648/j.stpp.20230702.14 AB - The COVID-19 pandemic affected all urban and rural areas across the globe. Particularly, the pandemic disrupted the material supply impacting all project schedules and project decisions. The purpose of this study is to analyze the materials delay impact due to COVID-19 pandemic on construction projects in terms of their schedule decisions. This study used an online questionnaire survey to collect the data from executive members of the construction companies within the United States. The survey focused on material supply and delivery delay questions organized in two subgroups using the Construction Specifications Institute MasterFormat divisions: (1) Facility Services and (2) Site and Infrastructure. Thirty-two responses from diverse company executive members were analyzed using t-test. The findings indicated that most of the projects were delayed due to either “Material and Labor” or “Material, Labor, and Equipment.” Thus, the two groups were analyzed in depth. The analysis shows that the mean delays were significantly higher for the “Material, Labor, and Equipment” group than the “Material and Labor” group. This is an important finding, suggesting that if similar situations arise, the project managers and/or the decision-makers should consider dedicating their time to the equipment required for those divisions and therefore mitigate delays. The study identifies crucial insights for successful project management during the pandemic, emphasizing the necessity of collaborating with subcontractors to secure essential equipment and address delays. It suggests expediting contract buyouts and submittals in vulnerable divisions to enhance resilience against material supply disruptions. Timely material procurement following project approvals for various durations is vital for minimizing pandemic-induced delays. Additionally, the study recommends adjusting lead times for materials with extended delivery timelines to mitigate construction delays associated with the pandemic. The lesson learned and recommendations from this study contributes to the body of knowledge in project management and project decision making by helping project managers and engineers to understand the impact and awareness of the challenges in material supply disruption during COVID-19 pandemic that could assist managers formulate appropriate strategies on future potential outbreaks. VL - 7 IS - 2 ER -